Project: Rotorua Airport
Main Contractor: Cushman & Wakefield
Location: Rotorua Airport
Year: Jan.2025
The Rotorua Airport Tower roof had experienced multiple leaks over the years, with numerous patch repairs and visible defects. After a thorough site inspection, we proposed a cost-effective solution: applying a liquid membrane system reinforced with fibreglass to address the ongoing leakage.
The roof was successfully tested for water-tightness upon completion, with all leaks resolved, ensuring a reliable solution and high client satisfaction.
The project faced challenges, including timing constraints and logistical hurdles due to the distance between Auckland and Rotorua, but our team overcame these with careful planning and coordination.